The efficient scheduling of resources in engineering construction projects: reflections on a case study from Iran

Greenwood, David and Gledson, Barry (2012) The efficient scheduling of resources in engineering construction projects: reflections on a case study from Iran. Construction Management and Economics, 30 (8). pp. 687-695. ISSN 0144-6193

Full text not available from this repository. (Request a copy)
Official URL: http://dx.doi.org/10.1080/01446193.2012.704595

Abstract

A particular problem for productivity in engineering construction projects is poor front-end planning, in particular, the lack of attention to resource-loaded schedules. In such projects, resources are highly specific and constrained, resulting in conflicts that can compromise planned durations and add cost. There are many techniques available for mitigating these conflicts. These have been extensively reported and compared in the literature and some have been adopted into commercially available computerized schedul- ing packages that are used by most major contractors. Project managers normally have access only to the techniques offered by the software that their organizations happen to use. In the reported case, a heuristic algorithm developed by academics was implemented and tested against a well-known standard software scheduling tool on the construction of a combined-cycle power plant in Iran. When results were compared, the performance of the manually applied algorithm was found to be superior in its ability to provide acceptable time–cost trade-offs. The underlying argument is twofold. First, that deficiencies in planning (particularly the reconciliation of resource constraints with completion targets) are responsible for poor productivity in engineering construction projects. Second, as improved techniques for optimizing ‘resource-loaded’ schedules are continually being sought and devised, they should be made available to project managers; and the best way for this to happen is for them to be incorporated into commercially available project management software.

Item Type: Article
Uncontrolled Keywords: Case study, heuristic algorithm, power plant construction, productivity, resource-loaded schedules
Subjects: K200 Building
Department: Faculties > Engineering and Environment > Mechanical and Construction Engineering
Depositing User: Barry Gledson
Date Deposited: 29 Oct 2012 10:17
Last Modified: 13 Oct 2019 00:32
URI: http://nrl.northumbria.ac.uk/id/eprint/10068

Actions (login required)

View Item View Item

Downloads

Downloads per month over past year

View more statistics