Construction Planning Efficiency and Delivery Time Performance: Analysing Failure in Task-Level ‘Hit Rates’

Gledson, Barry, Williams, David and Littlemore, Michelle (2018) Construction Planning Efficiency and Delivery Time Performance: Analysing Failure in Task-Level ‘Hit Rates’. In: ARCOM 2018: 34th Annual Conference - A Productive Relationship: Balancing Fragmentation and Integration, 3rd - 5th September 2018, Belfast, UK.

[img]
Preview
Text (Full text)
Gledson - Construction Planning Efficiency and Delivery Time Performance AAM.pdf - Accepted Version

Download (188kB) | Preview

Abstract

Construction project delivery is considered successful by contracting firms if scope, time, cost, and quality outputs are attained, with any shortcomings in one or more of these representing a failure of sorts. Focusing only on the criteria of 'time', it is noticeable that more recent research efforts have been concentrated on poor time predictability and performance aggregated at construction ‘industry-level’, but minimal attention is retained on planning efficiency at individual ‘project-level’. Yet it is precisely because time performance enactment of individual ‘projects’, and their ‘project phases’, ‘work packages’, and ‘construction tasks’ remains unsatisfactory that predictability of time at an industry level is also recorded as poor. The main aim of this work therefore was to advance the discussion of construction planning efficiency via an analysis of time performance on a small range of recently, and nearly, completed construction projects. Data were obtained from a convenience sample of several major UK contracting organisations, which allowed quantitative analysis to be employed by measuring planning- and delivery- efficiencies. The paper contributes through an explanation of the methods used, and discussion of the findings, which show how in this sample, planning and delivery efficiency is worse than previously considered, with an average of only 38% of project activities starting on and finishing on time. Evidencing such time-performance failure should inform further project- level predictability and productivity research.

Item Type: Conference or Workshop Item (Paper)
Uncontrolled Keywords: Construction planning, Failure, Measurement, Planning efficiency, Predictability, Productivity
Subjects: K200 Building
N100 Business studies
Department: Faculties > Engineering and Environment > Mechanical and Construction Engineering
Depositing User: Paul Burns
Date Deposited: 12 Sep 2018 14:56
Last Modified: 01 Aug 2021 09:33
URI: http://nrl.northumbria.ac.uk/id/eprint/35675